Trench Boxes Assembly Guide
ESC Trench Boxes Assembly Guide
ESC Trench Boxes are easy to assemble. It is advisable for users to strictly follow the procedures supplied by ESC.
A. Flat pack delivery

-
Ensure all pins and retaining clips are correctly fitted.
-
Use only certified lifting slings.
-
Assemble on flat ground.
-
Do not allow personnel to enter the box/shield while the excavator is moving the trench box/shield.
-
Always ensure the box/shield is evenly supported by the ground to avoid box/shield becoming unstable.
-
Do not use the box if panel, pins or spreaders are damaged.
B. Cut packing straps/lift top panel.

C. Erect 4 spreaders, insert pin and R-clip.

D. Place top panel, pins and R-clips.
.png)


E. Rotate Shield

F. Install completed shield on site.